June 25, 2006
Drywall "mudding" in progress.
Updated: Jun 27, 2006 4:12am PST
June 11, 2006
Siding and all internal wiring done.
Updated: Jun 14, 2006 4:09am PST
April 11, 2006
Plumbing and HVAC work in progress.
Updated: Apr 12, 2006 7:15pm PST
April 2, 2006
Doors and windows in, plumbing & HVAC nearly completed.
Updated: Apr 14, 2006 9:51am PST
March 11, 2006
140 Trucklaods of dirt added
Updated: Mar 12, 2006 8:28pm PST
March 7, 2006
Roof felt on, mechanicals starting
Updated: Mar 08, 2006 5:43am PST
February 9, 2006
Exterior framing complete. Main floor framing complete. House wrap a ...
Updated: Feb 10, 2006 4:13am PST
February 4, 2006
1st steel beam in place and start of framing.
Updated: Feb 04, 2006 3:43pm PST
January 29, 2006
Basement slab poured and plumbing rough-ins completed
Updated: Feb 04, 2006 3:36pm PST
January 22, 2006
Concrete walls stripped, waterproofing and termite protection applied.
Updated: Jan 22, 2006 5:33pm PST
January 15, 2006
Footers poured and foundation walls formed.
Updated: Jan 15, 2006 5:55pm PST
January 8, 2006
Ground breaking, and a view of the river
Updated: Jan 08, 2006 7:48pm PST
May 8, 2005
Initial Clearing
Updated: Jan 08, 2006 9:36am PST